Friday, June 26 2026 10:59
Alina Hovhannisyan

Armenia and Iran agreed to jointly oversee construction of 400 kV  power line

Armenia and Iran agreed to jointly oversee construction of 400 kV  power line

ArmInfo. Deputy Minister of Territorial Administration and Infrastructure of Armenia Narek Apitonyan received an Iranian delegation.

Among a number of energy cooperation issues, the main topic of  discussion was the progress of the Iran- Armenia 400 kV overhead  power line (OPL) and the corresponding substation.

The Deputy Minister expressed hope for the completion of construction  work as soon as possible. The Iranian side also noted the importance  of completing the project, which will increase electricity supplies.

Following the meeting, the parties agreed to jointly oversee the  project's implementation. It should be noted that last November, the  Armenian government issued a budget loan to the Iranian company  Sunir, which is building the 400-kilovolt Iran-Armenia power  transmission line. A contract was signed with the project contractor,  Sunir, by the state-owned enterprise High Voltage Networks of Armenia  back in July 2006, according to which the contractor was obligated to  carry out the design, supply, construction, installation, testing,  and commissioning of the third 400 kV power transmission line and the  corresponding substation in a comprehensive manner. The total cost of  the project is EUR106,847,237.51. Of this cost, EUR 86,447,914 is  financed by a loan from the Export Development Bank of Iran, and  EUR20,399,323.51 is financed by a loan from Sunir International FZE.  The project completion date was set for December 31, 2034. The  project's implementation will increase electricity flows between  Armenia and Iran from 350 MW to 1,200 MW, enhance the security,  reliability, and stability of Armenia's energy system, and enable the  full utilization of the Iran-Armenia gas pipeline capacity under the  Gas for Electricity program.

In early June of this year, the Minister of Territorial  Administration and Infrastructure (MTAI) of the Republic of Armenia,  David Khudatyan, reported that construction of the third Iran-Armenia  power transmission line was 80% complete.

ArmInfo previously reported that Armenia was conducting a barter  agreement with Iran, receiving 1 cubic meter of Iranian gas in  exchange for 3 kWh of electricity in the opposite direction. With the  construction of the third transmission line, these volumes will  increase significantly. However, the North-South Energy Corridor  project, designed to connect the power systems of Iran, Armenia,  Georgia, and Russia, has encountered a number of problems, primarily  related to frequent delays in the commissioning date. While the  Iran-Armenia power transmission line project was previously scheduled  for completion in late 2018, in late December 2021, responsible  authorities stated that the line would be ready by the end of 2024.  As for the Armenia-Georgia power transmission line, the parties have  not yet begun its construction.